Os pongo el email recibido hoy tal cual:
Greetings Miners!
On Monday (13/01/2014) we released an outline of our set roadmap, today as promised we will be releasing a timeline with dates on each aspect of the development process. This shows our commitment to transparency and gives a better idea on what exact stage we are on at all times. As we go through multiple developmental stages in parallel, we will be releasing regular detailed updates on our progress. Our next updates will be consistent developmental updates on what is being worked on and what has been achieved.
Timeline:
Project Start: 16/08/13
Project Finish: 15/07/14
Task Name
|
Duration | Start | Finish |
---|---|---|---|
Viper ASIC Miner Project
|
238 days | Tue 16/08/13 | Tue 15/07/14 |
Scrypt Core and Chip Architecture
|
15 days | Mon 06/01/14 | Fri 24/01/14 |
System Architecture
|
5 days | Mon 06/01/14 | Fri 10/01/14 |
FPGA Implementation and Testing
|
131 days | Tue 16/08/13 | Fri 14/02/14 |
ASIC Development
|
85 days | Mon 20/01/14 | Fri 16/05/14 |
Viper Miner Board Design
|
95 days | Mon 13/01/14 | Fri 23/05/14 |
Viper Miner Firmware Development & Testing
|
118 days | Wed 01/01/14 | Fri 13/06/14 |
Mechanical, Thermal & Misc
|
69 days | Mon 13/01/14 | Thu 17/04/14 |
System Assembly & Testing
|
2 days | Mon 16/06/14 | Tue 17/06/14 |
System Integration & Testing
|
20 days | Wed 18/06/14 | Tue 15/07/14 |
User Manual
|
12 days | Fri 18/04/14 | Mon 05/05/14 |